For the Olympic Video games 2024, Paris citizens and guests are present process demanding situations. My customary metro shuttle regimen is being impacted. On the other hand, I discovered some answers the usage of executive internet sites, newspaper articles and smartphone programs. As I stroll round Paris, the bleachers are being put in in former pedestrian spaces. The taxi motive force has warned me that bridges will likely be closed. Bus 86 already circles round a brand new path; scenic, after all, thru Ile-Saint-Louis.

Metro signage to inform stops stations closed or where to transfer for olympic events ColleensParis

The primary resolution is to discuss with the Ministère Chargée des Shipping‘s (Ministry for Transportation) webpage (Your browser can translate the web page into your language of selection). Positive roads, bridges, pedestrian motion, in addition to metro stations are involved till November 2024. Those stations are Concorde, Champs-de-Mars, Trocadéro, Invalides, Grand Palais et Alexandre III.

Fast Reference

Transportation Affect Dates

  • CONCORDE:
  • June 1: closure of visitors to cars, pedestrians and cyclists on Position de los angeles Concorde.
  • July 1: closure to visitors of the Pont du Carrousel.
  • July 15: closure to visitors of the Royal Bridge.
  • Might 17 to September 21 no switch to line 12 is imaginable.
  • June 17 to September 21: Strains 1 and eight will likely be closed at Concorde. The nearest station to Concorde is Madeleine; Line 1 Tuileries station closes.
  • August 29 to October 30: Restrictions will transform lighter .
  • CHAMPS-DE-MARS:
  • March 4 to July 24: On-site building. 
  • June 3: nearly whole closure of the Champ-de-Mars gardens.
  • July 1: closure to visitors of the Pont d’Iéna.
  • July 24: closure to visitors of the quai Jacques-Chirac.
  • September 19 to November 4: Restrictions will transform lighter.
  • TROCADÉRO:
  • June 10: Closure of United Countries Road to car and pedestrian visitors
  • July 1st: Closure of the Trocadéro gardens
  • Visitors closure (cars, pedestrians and bicycles) of Albert-de-Mun Road and the south of Wilson Road (between Albert-de-Mun and Position d’Iéna)
  • July 16: Closure to visitors (motorized cars, pedestrians and bicycles) of the Position du Trocadéro and the Iéna Bridge
  • July 21: Closure to visitors of cars at the Quai Jacques-Chirac (between Suffren and Bourdonnais avenues), the underground stays open to visitors
  • July 27 to October 8 Dismantling of the website. 
  • INVALIDES:
  • April 12 to June 17: On-site building. 
  • June 3 to ten: Closure of the Port des Invalides (Port of the Invalides).
  • June 17: closure of the College Side road between Fabert and Constantine
  • September 18 to October 30: Dismantling of the website.
  • GRAND PALAIS – ALEXANDRE III:
  • April 26 to June 3 On-site building  
  • Might 17: closure of the Alexandre-III bridge to car visitors (pedestrian visitors maintained at the upstream sidewalk)
  • Might 20: closure of the port of the Champs-Élysées
  • June 3-10: closure of the port of Les Invalides all the way through building
  • July 1 to September 21: The metro station Champs-Elysées – Clémenceau is closed.
  • September 12 to October 26: Dismantling of the website.

Further Data and main points at the paintings and stages from the Ministry of Shipping.